Circuit/System Verification



1. Observe the DTC information with a scan tool. DTC P0685 or P1682 should not set.



瀚慖f a DTC is set, refer to Diagnostic Trouble Code (DTC) List - Vehicle (See: Diagnostic Trouble Code Descriptions/Diagnostic Trouble



Code (DTC) List - Vehicle).



2. Engine operating, observe the DTC information with a scan tool. DTC P2147, P2148, P2150, P2151, P2153, P2154, P2156, P2157, P216B,



P216C, P216E, or P216F should not set.



3. Observe the scan tool Current Misfire Counter parameters. The Current Misfire Counters should not increment.



4. Ignition ON, observe the scan tool Cylinder 1-6 Injector Control Circuit Status parameters. Verify the Injector Control Circuit Status



parameters display OK.



5. Operate the vehicle within the Conditions for Running the DTC to verify the DTC does not reset. You may also operate the vehicle within the



conditions that you observed from the Freeze Frame/Failure Records data.



Circuit/System Testing



1. Ignition OFF, disconnect the appropriate multi-way harness connector X198 or X199, at the rear of the intake manifold.



2. Ignition ON, observe the appropriate scan tool Cylinder 1-6 Injector Control Circuit Status. The parameter should display Open.



瀚慖f not the specified value, test the appropriate high voltage supply circuit, ECM side, for a short to ground or the appropriate high voltage



control circuit, ECM side, for a short to voltage. If the circuits test normal, replace the K20 ECM.



3. Ignition ON, connect a test lamp between the appropriate high voltage supply circuit and the high voltage control circuit. The Injector



Control Circuit Status should transition from Open to OK.



瀚慖f not the specified value, test for the following conditions in the ECM side of the harness:



* An open/high resistance in the high voltage supply circuit



* An open/high resistance in the high voltage control circuit



* A short to ground in the high voltage control circuit



* A short to voltage in the high voltage supply circuit



瀚慖f the circuits test normal, replace the K20 ECM.



Note: Testing for the following steps is performed on the fuel injector side of the multi-way harness connector. It may be necessary to



remove the intake manifold to isolate the condition.



4. Ignition OFF, measure the resistance between the appropriate high voltage supply circuit and ground. The DMM should display OL ohm.



瀚慖f less than the specified range, test the high voltage supply circuit and the high voltage control circuit for a short to ground. If the



circuits/connections test normal, test or replace the appropriate Q17 fuel injector(s).



5. Test for 2-3 ohm between the appropriate high voltage supply circuit and high voltage control circuit.



瀚慖f less than the specified range, test for a short between the high voltage supply circuit and high voltage control circuit. If the



circuits/connections test normal, test or replace the appropriate Q17 fuel injector(s).



瀚慖f greater than the specified range, test the high voltage supply circuit and high voltage control circuit for an open/high resistance. If the



circuits/connections test normal, test or replace the appropriate Q17 fuel injector.



Component Testing



* Fuel Injector Solenoid Coil Test (LAU) (See: Powertrain Management/Fuel Delivery and Air Induction/Fuel Injector/Testing and Inspection



)Fuel Injector Solenoid Coil Test (LF1, LFW) (See: Powertrain Management/Fuel Delivery and Air Induction/Fuel Injector/Testing and



Inspection)



* Fuel Injector Balance Test (LAU) (See: Powertrain Management/Computers and Control Systems/Testing and Inspection/Component Tests



and General Diagnostics/Fuel Injector Balance Test)Fuel Injector Balance Test (LF1, LFW) (See: Powertrain Management/Computers and



Control Systems/Testing and Inspection/Component Tests and General Diagnostics/Fuel Injector Balance Test)



Repair Instructions



Perform the Diagnostic Repair Verification (See: Verification Tests) after completing the diagnostic procedure.



* Fuel Injection Fuel Rail Assembly Replacement - Bank 1 (LF1) (See: Powertrain Management/Fuel Delivery and Air Induction/Fuel



Rail/Service and Repair/Fuel Injection Fuel Rail Assembly Replacement - Bank 1)



* Fuel Injection Fuel Rail Assembly Replacement - Bank 2 (LF1) (See: Powertrain Management/Fuel Delivery and Air Induction/Fuel



Rail/Service and Repair/Fuel Injection Fuel Rail Assembly Replacement - Bank 2)



* Control Module References (See: Testing and Inspection/Programming and Relearning) for ECM replacement, setup, and programming

No comments:

Post a Comment