2010 Land Rover LR2 (LF) L6-3.2L Technical Service Bulletin # TECLTB00349 Date: 110322
Electrical, A/T - Battery Cable Routing With A/T R&R
No: LTB00349 (ISSUE 1)
22 MAR 2011
SECTION: 307
Cable Routing Change When Installing New Transmission
AFFECTED VEHICLE RANGE:
LR2 (LF)
VIN: 8H000212-AH172293
Model Year:
2008 - 2010
CONDITION SUMMARY:
Situation:
As a result of changes made to the transmission casing, the positive battery and starter solenoid cables routing and securing points have been
modified.
NOTE:
When replacing the transmission with a modified casing (part number LR021650 or LR023720 [or later]), the positive battery cable must be
replaced with part number LR023719 (or later) and re-routed with the starter solenoid cable to the revised securing points on the transmission
casing.
Action:
In the event it becomes necessary to install a new transmission (part number LR021650 or LR023720 [or later]), refer to the Repair Procedure
outlined below to install a new positive battery cable and properly route it with the starter solenoid cable.
PARTS:
LR023719 Battery positive cable Qty: 1
TOOLS:
Refer to Workshop Manual for any required special tools
WARRANTY:
NOTE:
Repair procedures are under constant review, and therefore times are subject to change; those quoted here must be taken as guidance only.
Always refer to DDW to obtain the latest repair time.
2010 Land Rover LR2 (LF) L6-3.2L Page 36
DDW requires the use of causal part numbers. Labor only claims must show the causal part number with a quantity of zero.
Normal Warranty policies and procedures apply
REPAIR PROCEDURE
REPLACE TRANSMISSION AND POSITIVE BATTERY CABLE
1. Refer to Workshop Manual, section 307-01: Automatic Transmission / Transaxle, and remove the transmission.
2. Refer to Workshop Manual, section 303-01A: Engine - 3.2L NA-16, and remove the intake manifold.
3. Disconnect the battery positive cable from the generator. (Figure 1)
4. Remove the positive battery cable.
5. Install the new positive battery cable: (Figure 2)
^ Route cable as indicated.
6. Connect the positive battery cable to the generator:
(Figure 1)
^ Tighten nut to l2Nm (8.85lbf ft).
7. Refer to Workshop Manual, section 303-01: Engine - 3.2L NA-16, and install the intake manifold.